Who manages the power plant and where is its equipment from? Latvia prepares new inspections 0

Politics
BB.LV
Электроподстанция на закате с панелью управления

Latvia plans to tighten safety requirements for connecting power plants and energy storage systems to the main electricity grid. Checks will be conducted not only on the owners of the facilities but also on the manufacturers of software and control systems. In some cases, connection may be prohibited, and already operating equipment may be disconnected from the grid.

Latvia is preparing to introduce additional cybersecurity and national security requirements for facilities connected to the electricity transmission system.

The relevant amendments to the Electricity Market Law have been developed by the Ministry of Climate and Energy. According to the LETA agency, the draft law is scheduled to be reviewed at a Cabinet meeting on Friday, November 6.

The changes will affect electricity producers, system operators for energy storage, and end consumers who apply for connection of equipment to the transmission network.

Owners and origins of control systems will be checked

According to the draft law, the electricity transmission system operator Augstsprieguma tīkls (AST) will be required to develop and publish cybersecurity requirements for information systems and energy equipment control systems.

When applying for connection, companies will have to disclose additional information, including:

  • the country of registration of the company and its management structure;
  • the citizenship of board and council members;
  • information about capital share owners and true beneficiaries;
  • the country of registration of manufacturers of information systems and control systems of the connected equipment.

Thus, the verification will concern not only the energy facility itself but also who owns it and who produces the systems responsible for its management.

What countries' equipment will be allowed for connection?

The draft law provides for restrictions on the countries of registration of applicants, equipment operators, and manufacturers of information systems and control systems.

They must be registered in countries that fall into one of the specified categories:

  • NATO countries;
  • European Union member states;
  • countries of the European Free Trade Association;
  • Indo-Pacific region countries cooperating with NATO.

For individuals, there is a requirement for citizenship of the relevant states. If the applicant or manufacturer of control systems does not meet the established conditions, AST will be obliged to refuse connection of the equipment.

Refusal will also follow if the applicant does not provide the necessary documents or information.

Equipment can be disconnected based on security service conclusions

A separate mechanism is provided for cases where there are doubts about the reliability of the information provided or its compliance with national security interests. If AST has reasonable suspicions, the operator will be obliged to seek a conclusion from the competent state security institution.

If the security service establishes that the electricity producer, storage operator, or end consumer poses a threat to Latvia's national security, AST will have to refuse connection. If the equipment is already connected to the network, it can be disconnected.

In addition, AST will have the right to refuse connection of facilities that do not meet the cybersecurity requirements established by the operator.

When will the new requirements come into force?

The draft law provides for a transitional period so that enterprises can prepare for the changes. After the relevant provision comes into force, AST will have six months to develop and publish new cybersecurity requirements.

Separate conditions are provided for existing and previously approved facilities.

Category of equipment Specified term or condition
New connections According to new rules after the relevant provisions come into force
Facilities for which technical requirements were issued earlier Possibility of connection regardless of the country of registration of control system manufacturers
Already connected equipment requiring replacement or significant modernization of systems Until December 31, 2029
Other operators subject to the relevant transitional provisions Until December 31, 2027

Thus, the new restrictions do not imply an immediate disconnection of all equipment that does not meet future requirements.

New rules will also affect cross-border power plants

The amendments also regulate the connection of facilities for the production and storage of electricity located simultaneously in Latvia and another EU state. To obtain a permit for the operation of such facilities, additional documents confirming compliance with the requirements of both countries will need to be submitted.

In particular, the State Environmental Service of Latvia will need to obtain a conclusion from the competent institution of another EU country regarding the project's compliance with its environmental impact assessment requirements. Documents regarding property rights outside Latvia, where the equipment will be located, will also be required.

Before starting operation, it will be necessary to confirm the facility's compliance with the requirements of the other country in terms of construction and state security.

If the cross-border installation is planned to be connected to the electricity grid of a neighboring state, the conclusion on compliance with Latvian regulatory requirements will be issued by the State Environmental Service.